Cement on the Second Floor’s Gotta be Set Tonight
Hence, its 9 pm and men are still at work.
Hence, its 9 pm and men are still at work.
Just like shaking a cake pan filled with batter and leveling surface to fill air pockets.
A temporary fence in accordance to safety standards to prepare for the third floor cement pouring.
Preparing the footings for the third floor.
The wonders of this tying system for wires over the rebars makes the job ten times faster.
Three days ago the insulation was laid. Today, the reinforced bars were installed together with the radiant heat pipes (red pipes). The warm water that passes through these red pipes will channel heat giving warmth on bare feet. Now, after many months waiting, there is a level floor to walk on. The possibility of twisting…